Installation & Commissioning Details
Power requirements/capacity
- DNO (Distribution Network Operator) fuse capacity: this is the fuse amp rating from the National Grid to your property.
If the fuse capacity is not sufficient, believe keeps it simple. We’ll apply to the DNO on your behalf. - Consumer Unit compatibility
This is the capacity your distribution board has and whether there is enough compatibility on the board to install a charger. - Site consumption rates
This is how much electricity your site typically consumes at any one time. - Peak Load
This is the typical amount being used when your site is consuming the most electricity. - Power Analysis
A further site visit may be required to install a power analyser monitoring device (typically monitoring electrical consumption over seven days to find peak usage). This service is also part of the free survey package.
Groundworks
The groundworks will cover up to £2,500 of groundworks costs. £2,500 covers 95% of installations.
- Excavation
All ground excavation works to be carried out should cables need to be routed in conduit/ducting. - Ducting/Conduit
All ducting/conduit supplied as is required. - EV charger pedestal/wall mounting
EV chargers require either wall or ground mounting. Wall mounting may involve the addition of a wall mounting plate and ground mounted chargers require a pedestal to allow the charger/charger pole to be bolted to a concrete structure-known as a pedestal. - Bollard Installation
Installation of a bollard where relevant to protect the charger from damage. - Re-surfacing
All resurfacing work to in sympathy with the site’s surrounding surfaces.
Wiring
Additional sub-distribution board/s, dynamic load balancing kit and armoured cable can increase this cost. Typically no more than £3,000. Don’t worry! believe has you covered up to this amount, a greater value would be highlighted in our survey.
- Cabling requirements
- Sub-distribution board/s
- Dynamic load balancing unit/s
- WiFi/SMS compatibility
If WiFi/SMS networks are not available, hard wiring to an existing network would incur a cost, detailed in our survey report.
Signage
Readability (BS EN 17210:2021)
- Visibility
- Placement
- Usage Instructions
- Bay Markings
Commissioning
- Electrical Testing
- Correct Signage Installed
- Charger Configuration
- Documentation and Certification
- Handover/Demonstration
Making sure you’re good to go with all testing completed, charger onboarded and paperwork signed off is the last, free part of the package.